gantt-schedule
gantt
title Mobile app release
dateFormat YYYY-MM-DD
axisFormat %b %d
tickInterval 1week
weekday monday
excludes weekends
todayMarker off
%% Working days only: `excludes weekends` pushes a task's end past every
%% Saturday and Sunday it would cross, and the chart shades those days.
%% `after` can name several tasks and starts where the latest of them ends,
%% so Integration waits for both API build and Screens. Ticks fall every
%% week, on a Monday, labelled by `axisFormat`. `todayMarker off` leaves out
%% the line that marks today, so the picture is the same whenever it is drawn.
%% A task's `click` works as a flowchart node's: a link or a callback.
%% A `vert` task is a vert marker: a line up the chart at its start and its
%% label below the axis, on no row. It is a timeline target by its id — the
%% author's (`gonogo`) or, written without one, Mermaid's own `taskN`, which
%% counts it like any other task written without an id (`task1` here).
section Backend
API design :done, api, 2024-05-06, 4d
API build :crit, apiBuild, after api, 8d
section App
Screens :active, screens, 2024-05-08, 7d
Integration :integ, after apiBuild screens, 5d
section Release
Beta testers :beta, after screens, 6d
Store review :review, after integ, 3d
Release :milestone, release, after review, 0d
Code freeze :vert, 2024-05-20, 0d
Go/no-go :vert, gonogo, 2024-05-29, 0d
click api href "https://example.com/api-spec"
timeline:
enter api fade, enter apiBuild slide-right
enter screens fade
enter integ slide-right, highlight apiBuild outline, enter task1 fade
enter beta fade, enter gonogo fade, enter review fade, unhighlight apiBuild
enter release fade, highlight release glow